Roy Hill MSA Road Upgrade

Upgrade and sealing of MSA Access Road, Carpark and Gatehouse.

Surface preparation for seal including scarify to 100mm, grade, blend, WA moisture surface condition with existing surface and compaction. cutback bitumen prime; 14/7mm double/double spray seal; pavement marking including adequate surface preparation/ mechanical brushing to ensure surface is clear of loose material and inert material prior to application.

Challenges

Unseasonal wet weather. Interface and Co-ordinate with RHH Mining operations and other contractors who use the MSA Access road and Gatehouse to ensure access is provided at all times.

Milestone Moments

Completed on time on budget despite experiencing abnormal wet weather delays

Feature Project

Roy Hill MSA Road Upgrade

Upgrade and sealing of MSA Access Road, Carpark and Gatehouse.